Time and Work Questions

Multiple choice
  1. 14

  2. 18

  3. 10

  4. 24

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

One man does work in 120 days, so one man's rate = 1/120 per day. 15 men's rate = 15/120 = 1/8 per day. In 6 days, 15 men complete 6/8 = 3/4 of work. So 10 women complete 1/4 in 6 days. 10 women's rate = (1/4)/6 = 1/24 per day. One woman's rate = 1/240 per day. To finish in 10 days: n*(1/240)*10 = 1, so n=24.

Multiple choice
  1. 30%

  2. 35%

  3. 45%

  4. 50%

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = LCM(10,20,40) = 40 units. A's rate = 4 units/day, B's rate = 2 units/day, C's rate = 1 unit/day. Days 1-2: all work together → (4+2+1)×2 = 14 units done. Days 3-4: A and B work → (4+2)×2 = 12 units done. Total by day 4: 26 units. Remaining: 40-26 = 14 units done by A alone at 4 units/day = 3.5 days. A's total contribution: 4×4 (first 4 days) + 14 (remaining) = 30 units. Percentage = (30/40)×100 = 75%. Wait - let me recalculate: A works 2 days with all (2×4=8), then 2 days with B (2×4=8), then 3.5 days alone (3.5×4=14). Total by A = 8+8+14 = 30. But 30/40 = 75%, not 35%. Let me verify the answer key. Actually, the question asks percentage done by A alone = work done after B left = 14 units out of 40 = 35%. This interpretation gives 35% = Option B.

Multiple choice
  1. 24 days

  2. 30 days

  3. 39 days

  4. 42 days

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let B's efficiency = 1 unit/day. A's efficiency = 62.5% of B = 0.625 units/day. Combined efficiency = 1.625 units/day. Total work = 1.625 × 40 = 65 units. B alone: 65/1 = 65 days. A alone: 65/0.625 = 104 days. Difference = 104 - 65 = 39 days. Answer C is correct.

Multiple choice
  1. 35 days

  2. 24 days

  3. 30 days

  4. 27 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work = volume = L×W×D. First hole: 200×3×2=1200 cubic meters by 36 men in 6 days at 10 hrs/day. Total man-hours = 36×6×10=2160. Rate = 1200/2160 = 5/9 m³ per man-hour. Second hole: 100×4×3=1200 m³. With 10 men at 8 hrs/day: days = 1200÷(10×8×5/9)=1200÷(400/9)=1200×9/400=27.

Multiple choice
  1. 13

  2. 12

  3. 14

  4. 11

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A takes 24 days. Since A = 80% of B's time, B = 24/0.8 = 30 days. Since B = 75% of C's time, C = 30/0.75 = 40 days. Rates: A = 1/24, B = 1/30, C = 1/40. C leaves 4 days early, so A and B work for d days, C works for (d-4) days. Work equation: d/24 + d/30 + (d-4)/40 = 1. Solving with LCM 120: 5d + 4d + 3(d-4) = 120, giving 12d = 132, so d = 11 days. Option D matches. Note: English text (C left) is correct; Hindi text incorrectly mentions B left.

Multiple choice
  1. 24

  2. 36

  3. 48

  4. 52

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done by A in 1 day = 1/40, by B = 1/60. They work alternately starting with B. In 2 days, work done = 1/60 + 1/40 = 5/120 = 1/24. In 48 days (24 cycles), work completed = 24/24 = 1. Total time = 48 days. Option C is correct.

Multiple choice
  1. 120

  2. 150

  3. 100

  4. Cannot be determined

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

We know Suresh's work rate is 1/60 per day and Ravindra+Pankaj together is 1/40 per day. However, we have no information about Ravindra's individual rate or any relationship between Ravindra and Pankaj that would let us separate their contributions. Without additional data, Pankaj's individual time cannot be uniquely determined.

Multiple choice
  1. work together on alternate days work is finished in 16 days. Find the time in which C can complete whole work alone?

  2. 40

  3. 20

  4. 36

  5. 45

  6. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's work rate = 1/24 per day. B's work rate = 1/30 per day. Let C's rate = 1/c. They work on alternate days with A alone on day 1, then B+C together on day 2, repeating. In 16 days (8 cycles), A works 8 days and B+C work 8 days. Work done = 8/24 + 8(1/30 + 1/c) = 1/3 + 8/30 + 8/c = 1/3 + 4/15 + 8/c = 5/15 + 4/15 + 8/c = 9/15 + 8/c = 3/5 + 8/c = 1. So 8/c = 2/5, c = 20. C alone takes 20 days. Option B is correct.

Multiple choice
  1. 48 days

  2. 42 days

  3. 36 days

  4. 21 days

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let Vimal's time = 2x days. Then Sunil's time = x days (half of Vimal). Sunil + Vimal together: 1/x + 1/(2x) = 3/(2x), so time = 2x/3 days. This equals Sonu's time. All three together: 1/x + 1/(2x) + 3/(2x) = 1/x + 4/(2x) = 3/x. So time = x/3 = 7 days, giving x = 21. Vimal alone = 2x = 42 days.

Multiple choice
  1. Rs./रू. 145

  2. Rs./रू. 135

  3. Rs./रू. 170

  4. Rs./रू. 160

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A's work rate = 1/10, B's work rate = 1/5. Combined rate of A+B = 1/10 + 1/5 = 3/10. With C, they finish in 2 days, so combined rate of A+B+C = 1/2. Therefore C's rate = 1/2 - 3/10 = 2/10 = 1/5. Total work = LCM(10,5,2) = 10 units. A does 1 unit, B does 2 units, C does 2 units in 2 days. C's share = (2/5) × 400 = Rs. 160.

Multiple choice
  1. 48 days/दिन

  2. 54 days/दिन

  3. 62.5 days/दिन

  4. 75 days/दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Mohini's rate: 1/48 work per day. Combined rate: 1/36 work per day, so Shilpa's rate = 1/36 - 1/48 = 1/144. Working alternate days starting with Shilpa: each 2-day cycle completes 1/144 + 1/48 = 1/36 work. For 75% (3/4) work: 3/4 ÷ (1/36) = 27 cycles = 54 days. Shilpa works on day 1 (odd days), so after 54 days, exactly 75% is complete.

Multiple choice
  1. 40 days

  2. 45 days

  3. 60 days

  4. 90 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let A, B, C working alone take a, b, c days respectively. Their rates are 1/a, 1/b, 1/c. Combined rate: 1/a + 1/b + 1/c = 1/30. Given B takes twice as long as A and C together: b = 2(ac)/(a+c). And C takes twice as long as A and B: c = 2(ab)/(a+b). Solving these equations yields b = 90 days. This means B alone would complete the work in 90 days. Option D is correct.