Time and Work Questions

Multiple choice
  1. 10

  2. 9

  3. 11

  4. 8

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

12 men complete work in 6 days, so 12×6 = 72 man-days are needed. 10 men + 21 women take 3 days: (10 men + 21 women) × 3 = 72 man-days equivalent. Let 1 woman's work = w. Then 10 men = 72/3 = 24 man-days per 3 days, so 10 men contribute 10×(man's work)×3. Men's rate = 72/12 = 6 work units/day, so each man = 0.5 units/day. Total work in 3 days by 10M+21W: 10×0.5×3 + 21w×3 = 72. Solving gives w = 1/3. Then 12 women's time: 12×(1/3)×t = 72, so t = 9 days.

Multiple choice
  1. 5

  2. 7

  3. 3

  4. 4

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work rate: 10 men = 1/7 work per day, 10 children = 1/14 work per day. So 1 child = 1/2 man. 5 men + 10 children = 5 + 5 = 10 men. 10 men complete work in 7 days, so answer is 7 days.

Multiple choice
  1. 10

  2. 14

  3. 15

  4. 9

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's efficiency = 1/20, B's = 1/30, C's = 1/60. In 3-day cycle: Day 1: A does 1/20, Day 2: A does 1/20, Day 3: A+B+C do 1/20+1/30+1/60 = 6/60. Total in 3 days = 8/60. In 15 days (5 cycles): 5 × 8/60 = 40/60 = 2/3. On day 15: A works, adding 1/20. Cumulative: 2/3 + 1/20 = 47/60. Work completed.

Multiple choice
  1. A : 150, B : 100, C : 150

  2. A : 100, B : 150, C : 150

  3. A : 150, B : 150, C : 100

  4. A : 100, B : 150, C : 100

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's work rate is 1/16, B's is 1/24. Together with C, their combined rate is 1/6, so C's rate = 1/16. The work ratio A:B:C is 1/16:1/24:1/16 = 3:2:3. In Rs. 400, A gets 150, B gets 100, C gets 150.

Multiple choice
  1. 12

  2. 10

  3. 15

  4. 18

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let Amit's time = a days, Bhanu = b days, Chirag = c days. Given b = a - 5, b = c + 4, and a + b = 2c. Solving: a = 18, b = 13, c = 9. Total work = LCM(18,13,9) = 234. Amit's rate = 13/day, Bhanu's = 18/day. Alternate days starting with Amit: Day 1-2 = 31 units, repeating 7.5 times gives 248 units in 9 days.

Multiple choice
  1. 6 days/दिन

  2. 12 days/दिन

  3. 8 days/दिन

  4. 9 days/दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

P and Q together complete work in 4 days, so their combined rate is 1/4 of the work per day. Since P does twice as much work as Q in the same time, let Q's rate be x and P's rate be 2x. Then 3x = 1/4, meaning x = 1/12. Therefore P's rate is 2/12 = 1/6 of the work per day, so P alone takes 6 days. The key insight is that work rates add up when people work together.

Multiple choice
  1. 44

  2. 43

  3. 34

  4. 66

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

8 men or 17 women can paint 1 house in 33 days. So 1 man's rate = 1/(8×33) houses/day, 1 woman's rate = 1/(17×33) houses/day. Combined rate of 12 men and 24 women = 12/(264) + 24/(561) = 1/22 + 1/23.33 ≈ 1/11.16 houses/day. For 3 houses: Days = 3/(1/11.16) ≈ 33.48 ≈ 34 days.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity II > Quantity I

  4. Quantity II ≥ Quantity I

  5. Quantity I = Quantity II or Relation cannot be established

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Work is constant, so (men × days) is constant. Therefore: (X-2)(2Y) = (X+6)(Y). Solving: 2XY - 4Y = XY + 6Y, so XY - 10Y = 0, giving Y(X - 10) = 0. Since Y cannot be 0, X = 10. Substituting back: (8)(2Y) = (16)(Y) gives 16Y = 16Y, which is satisfied for any positive Y. Thus X = 10 but Y cannot be uniquely determined, so the relationship cannot be established.

Multiple choice
  1. 20th day

  2. 21st day

  3. 22nd day

  4. None of the above

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let m, w, c be daily work of 1 man, 1 woman, 1 child. From given: 12m + 16w = 1/26, 10w + 18c = 1/20, 8m + 16c = 1/25. Solving this system and finding m + w + c, then using the pattern of work (n(n+1)/2 × (m+w+c) = 1), we get n = 21.

Multiple choice
  1. 20

  2. 40

  3. 60

  4. 50

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Given a=b-20, c=1.5b. Work equation: 12(1/a) + 16(1/b) = 1. Substituting a=b-20: 12/(b-20) + 16/b = 1. Solving: (12b + 16b - 320)/[b(b-20)] = 1, giving b² - 48b + 640 = 0, so (b-16)(b-40) = 0. b=40 (b≠16 since a would be negative). So c = 1.5×40 = 60 days. R alone takes 60 days.

Multiple choice
  1. None of these

  2. All statements together are sufficient

  3. Any two are sufficient

  4. I and II or III

  5. All statements together are not sufficient

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

From Statement II: 9 women do 3/5 work in 15 days, so 9 women do 1/5 work in 5 days, meaning 9 women complete work in 25 days. With Statement I giving efficiency ratio 2:1, we can find man and woman rates. Combined rate of 6 men and 5 women can be calculated. Statement III introduces a child and creates alternative solution paths. Either pair (I+II) or (II+III) is sufficient.

Multiple choice
  1. I alone

  2. I or II

  3. I and II together are not sufficient

  4. II alone

  5. I and II together

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A and B have efficiency ratio 1:2. Let A's rate = a, B's rate = 2a. Statement I: A + C together take 24 days, so their combined rate is 1/24. B + C together complete 80% in 12 days, so their combined rate is 0.8/12 = 1/15. We have: a + c = 1/24 and 2a + c = 1/15. Subtracting: a = 1/15 - 1/24 = (8-5)/120 = 3/120 = 1/40. So A takes 40 days alone. Statement I alone is sufficient. Statement II: If B's efficiency increases by 20%, new rate is 2.4a. B finishes 20% less work than A. This doesn't give us absolute values or time to complete specific work. Not sufficient.

Multiple choice
  1. Rs. 6750

  2. Rs. 2750

  3. Rs. 6050

  4. Rs. 7050

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Ramesh takes 18 days (6300/350), Santosh takes 30 days (7500/250). Their combined rate = 1/18 + 1/30 = 4/45 work per day. Total cost = (350+250) × 45/4 = 6750.

Multiple choice
  1. 20/9 days/दिन

  2. 11/9 days/दिन

  3. 3 days/दिन

  4. 4 days/दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Efficiency A:B:C = 6:2:1. B's rate = 1/10. Combined rate = 6/20 + 2/20 + 1/20 = 9/20 job per day. Time = 20/9 days.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity II > Quantity I

  4. Quantity II ≥ Quantity I

  5. Quantity I = Quantity II or Relation cannot be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Quantity I: From (A+B) = 1/40, (B+C) = 1/20, (C+A) = 1/30. Adding all: 2(A+B+C) = 1/40 + 1/20 + 1/30 = 13/120. So A+B+C = 13/240. B's rate = (A+B+C) - (A+C) = 13/240 - 1/30 = 3/240 = 1/80. B alone takes 80 days. Quantity II: A+B = 1/24 and A is 50% more efficient than B, so A = 1.5B. Then 2.5B = 1/24, B = 1/60. B alone takes 60 days. Since 60 < 80, Quantity II (smaller days) represents faster completion, so B's capacity is higher.