Multiple choice

A does a work in 12 days, B does half work. as A in twice time, C does one fourth work as A in 1.5 time. If they all work together to complete a work then what percent of total wage will A get ? (approx)

  1. 70.%

  2. 41.8%

  3. 52%

  4. 75

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work rates: A completes in 12 days, so rate = 1/12. B completes half work in twice A's time (24 days), rate = 1/48. C completes one-fourth work in 1.5× A's time (18 days), rate = 1/72. Total rate = 1/12 + 1/48 + 1/72 = 17/144. A's wage share = (1/12)/(17/144) = 12/17 = 70.6%, which rounds to approximately 70%.