Pipes and Cisterns Questions

Multiple choice
  1. $\displaystyle\frac{25}{48}$
  2. $\displaystyle\frac{5}{6}$
  3. $\displaystyle\frac{25}{36}$
  4. $\displaystyle\frac{12}{25}$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Pipe 1 rate = 1/12 per hour. Pipe 2 rate = 1/8 per hour. Combined rate = 1/12 + 1/8 = 2/24 + 3/24 = 5/24 per hour. In 2.5 (5/2) hours, the filled part is (5/24) * (5/2) = 25/48.

Multiple choice
  1. $\left( x-y \right)$
  2. $\left( y-x \right)$
  3. $\displaystyle\frac { xy }{ \left( x-y \right) }$
  4. $\displaystyle\frac { xy }{ \left( y-x \right) }$
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Rate of filling pipe = 1/x. Rate of emptying pipe = 1/y. Combined rate = 1/x - 1/y = (y - x) / xy. Time taken = 1 / (combined rate) = xy / (y - x).

Multiple choice
  1. $110\ minutes$
  2. $100\ minutes$
  3. $120\ minutes$
  4. $90\ minutes$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let the capacity be 300 units. A fills 5 units/min, B fills 4 units/min. Together they fill 9 units/min. With the third pipe C, they fill 300/50 = 6 units/min. So C empties 9 - 6 = 3 units/min. Time for C = 300 / 3 = 100 minutes.

Multiple choice
  1. $1$ hour
  2. $2$ hours
  3. $6$ hours
  4. $8$ hours
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A take x hours, then B takes x + 6 hours. Together, 1/x + 1/(x+6) = 1/4. Solving 4(x+6 + x) = x(x+6) gives 8x + 24 = x^2 + 6x, or x^2 - 2x - 24 = 0. Factoring gives (x-6)(x+4) = 0. Since time is positive, x = 6.

Multiple choice
  1. $20$ hours
  2. $25$ hours
  3. $35$ hours
  4. Cannot be determined

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let pipe A's rate be x. Then B works at 2x and C at 4x, so the combined rate is 7x. Since the tank fills in 5 hours, 7x = 1/5, giving x = 1/35. Pipe A alone therefore takes 35 hours.

Multiple choice
  1. $6$ hours
  2. $10$ hours
  3. $15$ hours
  4. $30$ hours
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let the rates of the pipes be 1/x, 1/(x-5), and 1/(x-9). The problem states the rate of the third pipe equals the sum of the first two: 1/(x-9) = 1/x + 1/(x-5). Solving this quadratic equation x^2 - 19x + 45 = 0 leads to x = 15 as the valid solution.

Multiple choice
  1. Only I and II

  2. Only II and III

  3. All I, II and III

  4. Any two of the three

  5. Even with all the three statements, answer cannot be given

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

To find the time taken by two pipes together, we need their individual rates. Statement II gives pipe A's rate, and Statement III gives pipe B's rate. Statement I is redundant as the capacity cancels out.

Multiple choice
  1. $10\ min.$
  2. $8\ min.$
  3. $12\ min.$
  4. $16\ min.$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Pipe A fills 1/24 per min, B fills 1/30 per min. In 8 mins, A and B fill 8 * (1/24 + 1/30) = 8 * (5/120 + 4/120) = 8 * 9/120 = 72/120 = 3/5. Remaining tank = 2/5. Pipe B fills 2/5 at 1/30 rate: (2/5) / (1/30) = 12 minutes.

Multiple choice
  1. $2\ hrs\ 15\ min$
  2. $4\ hrs\ 24\ min$
  3. $5\ hrs$
  4. $3\ hrs$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Pipe A fills 1/4 of the tank per hour, and Pipe B fills 1/5 per hour. In two hours (one hour each), they fill 1/4 + 1/5 = 9/20 of the tank. After 4 hours, they have filled 18/20 = 9/10 of the tank, leaving 1/10 to be filled by Pipe A, which takes 1/10 / (1/4) = 0.4 hours or 24 minutes.

Multiple choice
  1. $8640$
  2. $8500$
  3. $4320$
  4. $60\ hours$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let the capacity be C. The leak empties at C/8 per hour. With the tap adding 6 liters/min (360 liters/hour), the net rate is C/12. So, C/8 - 360 = C/12. Solving for C: C/8 - C/12 = 360, which simplifies to C/24 = 360, so C = 8640 liters.

Multiple choice
  1. $5h$
  2. $4h$
  3. $5h$ $24min$
  4. $3h$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work rates: A = 1/10, B = 1/12. In 3 hours, A+B do 3 * (1/10 + 1/12) = 3 * (11/60) = 33/60 = 11/20. Remaining work = 9/20. B takes (9/20) / (1/12) = 9/20 * 12 = 108/20 = 5.4 hours, which is 5 hours 24 minutes.

Multiple choice
  1. $\frac { 1 }{ 40 } $
  2. $\frac { 1 }{ 30 } $
  3. $\frac { 1 }{ 35 } $
  4. $\frac { 1 }{ 8 } $
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

The filling rate is 1/8 of the cistern per hour, while the emptying rate is 1/10 per hour. Their net rate is 1/8 - 1/10 = 1/40 of the cistern per hour.