Pipes and Cisterns Questions

Multiple choice
  1. 20

  2. 24

  3. 30

  4. 36

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

18 pipes fill tank in 20 minutes. This is an inverse proportion: more pipes = less time. 18 × 20 = X × 15, where X is required pipes. X = (18 × 20)/15 = 360/15 = 24 pipes. The work (filling the tank) is constant. Pipes × Time = Constant. When time decreases from 20 to 15 minutes (factor of 3/4), pipes must increase by factor 4/3: 18 × 4/3 = 24.

Multiple choice
  1. 25 minutes/मिनट

  2. 18 minutes/मिनट

  3. 30 minutes/मिनट

  4. 40 minutes/मिनट

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

When pipes work together, their rates add up. Pipe A's rate is 1/20 tank per minute. The combined rate of A and B is 1/12 tank per minute. Therefore, B's rate is 1/12 - 1/20 = 1/30 tank per minute, which means B alone takes 30 minutes to fill the tank.

Multiple choice
  1. 2 hours

  2. 2.5 hours

  3. 3 hours

  4. 3.5 hours

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

First pipe fills in 40 minutes (rate = +1/40 tank per minute). Second pipe empties in 60 minutes (rate = -1/60 tank per minute). Combined rate = 1/40 - 1/60 = (3-2)/120 = 1/120 tank per minute. Time to fill = 120 minutes = 2 hours.

Multiple choice
  1. 200 hr

  2. 250 hr

  3. 350 hr

  4. 450 hr

  5. 500 hr

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

The tank volume needed is 200 × 150 × 8 = 240,000 m³. The pipe cross-section is 0.3 × 0.2 = 0.06 m² and water flows at 20 km/h = 20,000 m/h, giving a flow rate of 0.06 × 20,000 = 1,200 m³/h. Time = volume/flow rate = 240,000/1,200 = 200 hours.

Multiple choice
  1. 6

  2. 8

  3. 11

  4. 13

  5. None of these

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

In 21 hours (3 cycles of 7 hours each): A, B, C work for 3 hours each, drainage works for 3 hours. Net work = 3*(1/12 + 1/20 + 1/16) - 3/D = 43/60 - 3/D. Remaining work in hour 22 (A) + 23 (B): 1/12 + 1/20 = 8/60. Total work = 43/60 + 8/60 = 51/60. Remaining 9/60 done by C in 24th hour, but drainage opens in 22nd hour. The correct drainage rate is 40/3 hrs (approximately 13.33), which is not in options A-D.

Multiple choice
  1. 6 min./मि.

  2. 7 min./मि.

  3. 2 min./मि.

  4. 5 min./मि.

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Pipe A fills at 3 lit/min, taking 14 min, so tank capacity = 3×14 = 42 lit. Pipe B fills at 4 lit/min. Combined rate = 3+4 = 7 lit/min. Time = 42/7 = 6 min. Options B, C, D are incorrect.

Multiple choice
  1. 20 l/ली.

  2. 24 l/ली.

  3. 26 l/ली.

  4. 28 l/ली.

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let B's rate be x L/min, so A's rate is 4x L/min. Together: 5x = 7, so x = 1.4 and A's rate = 5.6 L/min. Time ratio: 5.6t₁ = 1.4t₂ (same work), with t₂ - t₁ = 15. Solving gives bucket = 28 litres. This is a work and time problem with efficiency ratios.

Multiple choice
  1. 20

  2. 18

  3. 15

  4. 12

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let slower pipe take x hours, so faster takes (x-10) hours. Together: 1/x + 1/(x-10) = 1/12. Solving: (2x-10)/[x(x-10)] = 1/12, giving x² - 10x = 24x - 120, so x² - 34x + 120 = 0. This gives x = 30 (valid) or x = 4 (invalid as x-10 would be negative). Faster pipe takes 30-10 = 20 hours.

Multiple choice
  1. 24 hrs.

  2. 36 hrs.

  3. 48 hrs.

  4. 62 hrs.

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Combined rate of A + B = 1/5 + 1/20 = 1/4 tank per hour (4 hours to fill). With hole, it takes 4.5 hours, so effective rate = 2/9 per hour. Hole's rate = 1/4 - 2/9 = 1/36 per hour (emptying). The hole alone empties the full tank in 36 hours.

Multiple choice
  1. 205 m./मिनट

  2. 192 m./मिनट

  3. 184 m./मिनट

  4. 164 m./मिनट

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let slower pipe time = x minutes. Then faster pipe time = x/3 minutes (3 times faster). Their combined rate: 1/x + 3/x = 4/x = 1/48 (since together they fill in 48 min). Solving: 4/x = 1/48, so x = 192 minutes for slower pipe alone.

Multiple choice
  1. 45 hours

  2. 60 hours

  3. 75 hours

  4. 90 hours

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Combined rate of A and B: 1/36 tank per hour. In first scenario: A+B work for 30 hours, then A works alone for 10 hours (total 40 hours). So 30(1/36) + 10(1/A) = 1 tank, where 1/A is A's rate. This gives 5/6 + 10/A = 1, so 10/A = 1/6 and A alone takes 60 hours. Since 1/A + 1/B = 1/36, we have 1/60 + 1/B = 1/36, giving 1/B = 1/36 - 1/60 = 1/90. So B alone takes 90 hours. Option D is correct.

Multiple choice
  1. 7 minutes/ मिनट

  2. 5 minutes/ मिनट

  3. 8 minutes/ मिनट

  4. 3 minutes/ मिनट

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

K fills in 21 min, so rate = 1/21. L is 6 times faster: rate = 6/21. Combined rate = 7/21 = 1/3. Time = 3 minutes. Option D is correct.

Multiple choice
  1. 4 hours 45 minutes/4 घंटे 45 मिनट

  2. 4 hours /4 घंटे

  3. 3 hours 45 minutes/3 घंटे 45 मिनट

  4. 45 minutes/45 मिनट

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The Hindi text (6 hours) contradicts the English text (12 hours). Using 6 hours: half tank fills in 3 hours by one pipe. Remaining half is filled by 4 pipes in 0.75 hours (3/4). Total time = 3 + 0.75 = 3 hours 45 minutes. When n similar pipes work together, time reduces by factor 1/n.

Multiple choice
  1. 45 hours/घंटे

  2. 50 hours/घंटे

  3. 60 hours/घंटे

  4. 75 hours/घंटे

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Pipe I fills 3/5 of tank in 18 hours, so it fills the whole tank in 18 × 5/3 = 30 hours. Pipe I's efficiency is 2.5 times Pipe II's efficiency, so Pipe II takes 2.5 × 30 = 75 hours to fill the tank alone. Therefore, the answer is 75 hours.