Multiple choice

A project has six activities (A to F) with respective activity durations 7, 5, 6, 6, 8, 4 days. The network has three paths A-B,C-D and E-F. All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is

  1. 1

  2. 2

  3. 3

  4. 6

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The 3 activity need to be crashed to reduce the project duration by 1 day