  • Consider the given project network, where numbers along v...
Multiple choice

Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4-6 and the project duration, respectively, are

  1. 2, 13

  2. 0, 13

  3. – 2, 13

  4. 2, 12

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Correct option is (1).

Keep practicing — related questions

  • Following data refers to the activities of a project, where node 1 refers to the start and node 5 refers to...
  • The precedence relations and duration (in days) of activities of a project network are given in the table. ...
  • A project has six activities (A to F) with respective activity durations 7, 5, 6, 6, 8, 4 days. The network...
  • For a particular project eight activities are to be carried out. Their relationships with other activities ...
  • Directions: Which of the given options best represents the information in the given reading passage? Choose...
  • Directions: Which of the given options best represents the information in the given reading passage? Choose...
  • Directions: Which of the given options best represents the information in the given reading passage? Choose...
  • Directions: Which of the given options best represents the information in the given reading passage? Choose...
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy