For a particular project eight activities are to be carried out. Their relationships with other activities and excepted durations are mentioned in the table below:
Activity| Predecessors| Duration (days)| | a| -| 3| | b| a| 4| | c| a| 5| | d| a| 4| | e| b| 2| | f| d| 9| | g| c, e| 6| | h| f, g| 2|
If the duration of activity f alone is changed from 9 to 10 days, then the