Multiple choice

The precedence relations and duration (in days) of activities of a project network are given in the table. The total flot (in days) of activities e and f, respectively, are

   
Activity Predecessors Duration (days)
a - 2
b - 4
c a 2
d b 3
e c 2
f c 4
g d, e 5

  1. 0 and 4

  2. 1 and 4

  3. 2 and 3

  4. 3 and 1

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Correct option is (2).