  • Mechanical Engg. (GATE) 2006
  • Consider a PERT network for a project involving six tasks...
Multiple choice

Consider a PERT network for a project involving six tasks (a to f).

The expected completion time of the project is

  1. 238 days

  2. 224 days

  3. 171 days

  4. 155 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Keep practicing — related questions

  • Consider a PERT network for a project involving six tasks (a to f). ![](https://i.imgur.com/16M4M9Z.png) Th...
  • Consider the following PERT network: ![](https://i.imgur.com/1jW2kIl.png) The optimistic time, most likely ...
  • Which of the following types of operating systems are required to complete a critical task within a gaurant...
  • Consider the following facts: 1. The Shimsa hydroelectric project was the first ever hydro-electric project...
  • A teachers tries to involve her students in many group based activities such as group discussion, group pro...
  • Directions: Choose the correct word/phrase to complete the given sentence. How ________ time does it take t...
  • Directions: Based on the information from the paragraph, choose the appropriate number 1 – 4 to complete th...
  • Select the correct answer to complete the following sentence. If I have time, _____________.
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy