aliensbrain
  • Home
  • Study
  • Quizzes
  • 🎤AI Practicefree
  • Notebooks
  • Community
  • Sign in
  • Mechanical Engg. (GATE) 2009
  • Consider the following PERT network: ![](https://i.imgur....
Multiple choice

Consider the following PERT network:

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

The critical path duration of the network (in days) is

  1. 11

  2. 14

  3. 17

  4. 18

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Hence, The expected duration of the critical path is 18 days.

Keep practicing — related questions

  • Consider the following PERT network: ![](https://i.imgur.com/c3OKx66.png) The optimistic time, most likely ...
  • The expected time (te) of a PERT activity in terms of optimistic time (t0), pessimistic time (tp) and most ...
  • Consider a PERT network for a project involving six tasks (a to f). ![](https://i.imgur.com/16M4M9Z.png) Th...
  • Following data refers to the activities of a project, where node 1 refers to the start and node 5 refers to...
  • Consider a PERT network for a project involving six tasks (a to f). ![](https://i.imgur.com/yYFpB2A.png) Th...
  • Which of the following is considered an alternative energy?
  • Which of the following is a benefit of the just in time method to manage working capital?
  • To be considered a full-time employee you must work more than _____ hours a week.
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy