  • Mechanical Engg. (GATE) 2009
  • Consider the following PERT network: ![](https://i.imgur....
Multiple choice

Consider the following PERT network:

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

The standard deviation of the critical path is

  1. 0.33

  2. 0.55

  3. 0.77

  4. 1.66

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Keep practicing — related questions

  • Consider the following PERT network: ![](https://i.imgur.com/1jW2kIl.png) The optimistic time, most likely ...
  • Consider a PERT network for a project involving six tasks (a to f). ![](https://i.imgur.com/16M4M9Z.png) Th...
  • The expected time (te) of a PERT activity in terms of optimistic time (t0), pessimistic time (tp) and most ...
  • Following data refers to the activities of a project, where node 1 refers to the start and node 5 refers to...
  • Consider a PERT network for a project involving six tasks (a to f). ![](https://i.imgur.com/yYFpB2A.png) Th...
  • Consider the following statements: 1. A passive optical network is a point-to-point optical network. 2. A g...
  • Consider the following statements: 1. Antibodies are also received by foetus from mother's milk. 2. Antibod...
  • Consider the following statements about alachlor: 1. It is a pesticide. 2. It is used for the control of we...
Play the full quiz 🎤 Practise this topic out loud

Practice this topic

  • Statistics and Dispersion (559 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy