Multiple choice

Consider a PERT network for a project involving six tasks (a to f).

The standard deviation of the critical path of the project is

  1. $\sqrt{151}$ days
  2. $\sqrt{155}$ days
  3. $\sqrt{200}$ days
  4. $\sqrt{238}$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Keep practicing — related questions

  • Consider the following PERT network: ![](https://i.imgur.com/c3OKx66.png) The optimistic time, most likely ...
  • Consider a PERT network for a project involving six tasks (a to f). ![](https://i.imgur.com/yYFpB2A.png) Th...
  • Consider the following PERT network: ![](https://i.imgur.com/1jW2kIl.png) The optimistic time, most likely ...
  • Following data refers to the activities of a project, where node 1 refers to the start and node 5 refers to...
  • For a particular project eight activities are to be carried out. Their relationships with other activities ...
  • Consider the following facts: 1. The Shimsa hydroelectric project was the first ever hydro-electric project...
  • The ___________ network management task assumes that access to network resources is controlled and the data...
  • Consider the following statements: 1. A passive optical network is a point-to-point optical network. 2. A g...
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy