Directions: Choose the correct option for the given question:Consider the following statements in respect of PERT.
- PERT is a variation of milestone budgeting.
- PERT employs probabilistic estimate of time required for completion of an activity.
- PERT also includes the transfer of resources for reduction of duration of completion of a project. Which of the statements given above are correct?