Multiple choice

How are PERT charts used for project management?

  1. Size estimation

  2. Cost estimation

  3. Scheduling

  4. Complexity analysis

  5. Reliability requirements

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

PERT stands for Program Evaluation Review Technique. A PERT chart is a project management tool that is used to schedule, organise, and coordinate tasks within a project.