The completion of which of the following events is most likely to be designated as a project milestone?

  1. a critical activity

  2. a peer review

  3. a phase gate review

  4. a test case

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A phase gate review is a key project review marking the transition between project phases, making its completion a major milestone. A critical activity is a task on the critical path rather than a milestone, while a peer review or a test case represents individual tasks that do not signify phase transition.