Multiple choice six-sigma green-belt

A detailed plan of key steps and dates are defined in

  1. Goal Statement

  2. Project Scope

  3. Project Milestones

  4. Problem Statement

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Project Milestones define key deliverables with target dates throughout a project timeline. Goal Statements state objectives, Project Scope defines boundaries, and Problem Statements describe issues - none provide detailed step-by-step plans with dates.