"The following are Customer Research Toolexcept _____"

  1. Surveys

  2. Interviews

  3. Listening Post

  4. FMEA


Correct Option: D
  1. Specification Limits

  2. Control Limits

  3. Targets

  4. None of above


Correct Option: B
  1. 1 Sample t-Test

  2. 2 Sample t-Test

  3. Analysis Of Variance (ANOVA)

  4. Chi Square test


Correct Option: A
  1. Affinity Diagram

  2. Customer Segmentation

  3. Consensus

  4. Sampling


Correct Option: A
  1. Screening Experiments

  2. Fractional Factorials

  3. Full Factorials

  4. None of above


Correct Option: C
  1. alternate path flowchart

  2. Process Flowchart

  3. Deployment flowchart

  4. cross-functional map


Correct Option: A
  1. Simulation

  2. CAP

  3. Cost Benefit Analysis

  4. FMEA


Correct Option: A
  1. CAP

  2. FMEA

  3. Control Impact Matrix

  4. TRIZ


Correct Option: C
  1. LSL & USL are three standard deviations away from the mean

  2. Six standard deviations between LSL & USL

  3. Six standard deviations between mean and farthest specification limit

  4. 12 standard deviations between LSL and USL


Correct Option: D

A "SMART" Goal is

  1. Specific, Measurable, Ambitious, Realistic, Timebound

  2. Specific, Measurable, Attainable, Realistic, Timebound

  3. Special, Measurable, Attainable, Realistic, Timebound

  4. Special, Measurable, Ambitious, Realistic, Timebound


Correct Option: B
  1. Run chart

  2. Histogram

  3. Check Sheet

  4. Process Map


Correct Option: B

A detailed plan of key steps and dates are defined in

  1. Goal Statement

  2. Project Scope

  3. Project Milestones

  4. Problem Statement


Correct Option: C
  1. Special Cause Variation

  2. Total Observed Variation

  3. Common cause Variation

  4. Unexplained Variation


Correct Option: C

A GB is having 3 factors X1, X2 and X3. Factors X1 and X2 are having 3 levels and the factor X3 is having 4 levels. What should be the number of trials?

  1. 10

  2. 16

  3. 36

  4. 13


Correct Option: C

Which one of the following is not carried out in Improve?

  1. Generation of solutions

  2. Testing of solution

  3. Handover to process owner

  4. Selection of solutions


Correct Option: C

Which one of the following is not considered as a Tangible Benefit

  1. Cost Avoidance

  2. Incremental revenue

  3. Cost Savings

  4. Interest


Correct Option: A

Which one of the following is not true

  1. Control limits are given by customer

  2. Control limits are calculated from the data

  3. Control limits change when there is a significant change in the process

  4. Control limits represent the voice of the process


Correct Option: A
  1. Continuous data gives more understanding of the process

  2. Discrete data gives more understanding of the process

  3. Neither is good to understand a process

  4. Discrete data is always repeatable


Correct Option: A

Which one of the following is TRUE?

  1. Smaller the variation, less the chances of defect occurrence

  2. Smaller the mean, smaller will be the Process Sigma

  3. Smaller the standard deviation, larger will be the process variation

  4. Smaller the mean, smaller will be the variation


Correct Option: A

ZLT =

  1. Zst + 1.5

  2. Zst - 1.5

  3. Zst

  4. 6 Sigma


Correct Option: B