Multiple choice technology testing

Why RPT Received Criticism in the Earlier Launch?

  1. It finished the amount of work in no time and therefore caused waste of time

  2. It caused huge expenditure

  3. It could not find an issue if a system performance bottleneck exists in an untested area.

  4. The testers were not able to understand the functionality of the Tool

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

RPT received criticism in its early launch because it could only detect performance bottlenecks in areas that were specifically tested. If a bottleneck existed in an untested part of the system, RPT would not find it - this was a significant limitation for comprehensive performance assessment.