PCRs are generally signed off during

  1. Beginning of the Project

  2. End of the Project

  3. Beginning of the testing

  4. End of Development

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A Project Completion Report (PCR) is a formal document that signals the official closure of a project. Consequently, it is signed off at the End of the Project to confirm all deliverables are met. Signing it at the beginning or during development/testing stages would be premature and incorrect.