Testing should be stopped when:

  1. a) all the planned tests have been run

  2. b) time has run out

  3. c) all faults have been fixed correctly

  4. d) both a) and c)

  5. e) it depends on the risks for the system being tested

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Testing completion depends on risk assessment and acceptable quality thresholds for the system being tested, not on running all planned tests (A), time limits (B), or fixing all faults (C) which may be impractical. Option E correctly states testing stops when risks are mitigated to acceptable levels.