What should be done by the project manager to ensure that all work in the project is included?

  1. Create a contingency plan

  2. Create a risk management plan

  3. Create a WBS

  4. Create a scope statement


Correct Option: C

AI Explanation

To answer this question, you need to understand the concept of project management and the tools used to ensure that all work in a project is included.

Option A) Create a contingency plan - This option is incorrect because a contingency plan is a plan designed to handle potential risks or issues that may arise during the project execution. While it is important to have a contingency plan, it does not directly ensure that all work in the project is included.

Option B) Create a risk management plan - This option is incorrect for the same reason as Option A. A risk management plan focuses on identifying, assessing, and mitigating risks in the project, but it does not directly ensure that all work is included.

Option C) Create a WBS - This option is correct. A WBS (Work Breakdown Structure) is a hierarchical decomposition of the project deliverables into smaller, more manageable components. By creating a WBS, the project manager can ensure that all work in the project is included and properly organized.

Option D) Create a scope statement - This option is incorrect. A scope statement defines the boundaries and objectives of the project, but it does not provide a detailed breakdown of all the work required. The creation of a scope statement is an important step in project management, but it does not directly ensure that all work is included.

The correct answer is C) Create a WBS. This option is correct because a WBS helps the project manager to systematically break down the project into smaller work packages, ensuring that all work is included and accounted for.