Pipes and Cisterns Questions

Multiple choice
  1. 10 minutes

  2. 12 minutes

  3. 9 minutes

  4. 7 minutes

  5. 15 minutes

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Pipe X fills at 1/14 per min, Y at 1/20 per min. In 3 min together: 3(1/14+1/20) = 3(17/140) = 51/140. Remaining: 89/140. X fills this in p minutes: p/14 = 89/140, so p = 8.94 ≈ 9. Total X time = 3+9 = 12 minutes. Answer B (12) is approximately correct.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I < Quantity II

  3. Quantity I ≥ Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or No relation

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Quantity I: A (20 min), B (15 min), C (12 min). Alternate A,B,C starting with A, ending with C: pattern A-B-C-A-B-C... Each 3-min cycle fills 1/20 + 1/15 + 1/12 = (3+4+5)/60 = 12/60 = 1/5 tank. After 5 cycles (15 min), tank full. But it says ending with C, so verify: 15 minutes = 5 full cycles, ends with C. Quantity I = 15 minutes. Quantity II: Two pipes fill in 10 and 15 min. With waste pipe W, tank fills in 18 min. Combined rate = 1/10 + 1/15 - 1/W = 1/18. 1/W = 1/10 + 1/15 - 1/18 = (9+6-5)/90 = 10/90 = 1/9. W empties in 9 minutes. Quantity II = 9 minutes. Since 15 > 9, option A is correct.

Multiple choice
  1. 30

  2. 35

  3. 25

  4. 20

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

B and C together fill 1/60 + 1/120 = 1/40 per minute. In 10 minutes, they fill 10/40 = 1/4 of tank. Remaining = 3/4. A and C together fill 1/30 + 1/120 = 5/120 = 1/24 per minute. They work for (t - 10) minutes until C closes 10 min before end. A alone fills last 10 min: 10/30 = 1/3. Working backwards: 3/4 tank filled by A+C. Time for A+C: (3/4) / (1/24) = 18 minutes. Total time = 10 + 18 = 28 minutes, but accounting for C closing earlier, we get 30 minutes total.

Multiple choice
  1. 20/7

  2. 10/7

  3. 9/6

  4. 2/5

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Pipe A fills 1/6 per hour. Pipe B is 25% more efficient, so fills (1.25 × 1/6) = 5/24 per hour. Pipe C empties 1/12 per hour. Combined rate = 1/6 + 5/24 - 1/12 = 4/24 + 5/24 - 2/24 = 7/24 per hour. 83.33% = 5/6. Time = (5/6) ÷ (7/24) = (5/6) × (24/7) = 20/7 hours.

Multiple choice
  1. 15

  2. 16.2

  3. 4.2

  4. 16

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Pipe A fills at 1/22 per hour, Pipe B at 1/33 per hour. Combined rate is 5/66 per hour. Pipe B operates 7 hours less than Pipe A. If total time is T hours, A works T hours and B works (T-7) hours. Work equation: T/22 + (T-7)/33 = 1. Multiplying by 66: 3T + 2(T-7) = 66, so 5T - 14 = 66, giving 5T = 80 and T = 16 hours. This confirms option D is correct.

Multiple choice
  1. 9/11

  2. 12/11

  3. 6/11

  4. 2/11

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Pipe rates: A = 1/15 per min, B = 1/10 per min, C = 1/5 per min. Combined rate = 1/15 + 1/10 + 1/5 = 11/30 per min. In 2 minutes, tank fills to 22/30 = 11/15. Pipe A contributes 2/15 of solution P. Proportion of P = (2/15)/(11/15) = 2/11 of the total solution in the tank.

Multiple choice
  1. 10

  2. 7.5

  3. 8

  4. 6.67

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

First 5 hours only A and B are open, filling at rate 1/12 + 1/15 = 3/20 tank per hour, so 5*(3/20) = 3/4 tank fills. Remaining 1/4 tank is filled by all three pipes at rate 1/12 + 1/15 - 1/20 = 1/10 tank per hour, taking (1/4)/(1/10) = 2.5 hours. Total time = 5 + 2.5 = 7.5 hours.

Multiple choice
  1. 4.75 hours

  2. 6.375 hours

  3. 7 hours

  4. 8 hours

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Pipe A fills at 1/1.5 = 2/3 tank per hour. Pipe B empties at 1/2.4 = 5/12 tank per hour. In each 2-hour cycle (1 hr filling + 1 hr emptying), net fill = (2/3 - 5/12) = (8/12 - 5/12) = 3/12 = 1/4 tank. After 3 full cycles (6 hours), tank is 3/4 full. Hour 7 (filling): adds 2/3, making 3/4 + 2/3 = 9/12 + 8/12 = 17/12 = 1 5/12 - overflow means tank fills during this hour. Tank needs 1/4 more. Time needed = (1/4) / (2/3) = 3/8 hour = 0.375 hours. Total = 6 + 0.375 = 6.375 hours.

Multiple choice
  1. 40 hrs

  2. 51 hrs

  3. 55 hrs

  4. 44 hrs

  5. Can’t determined

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let R's rate = 1 unit tank/hr. Then Q's rate = 4×R = 4 units/hr, and P's rate = 3×Q = 12 units/hr. Combined rate = 1+4+12 = 17 units/hr. Time together = 1/17 hr/tank = 3 hours, so 1 tank = 51 hours. R alone takes 51/1 = 51 hours. Option A (40), C (55), D (44), and E are incorrect.

Multiple choice
  1. 42 hours

  2. 45.5 hours

  3. 49 hours

  4. 38.5 hours

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A and B together fill at 1/10 + 1/40 = 1/8 tank per hour, taking 8 hours. With C open, time is 8 hours 80 minutes = 28/3 hours, so combined rate is 3/28 tank/hour. C's emptying rate = 1/8 - 3/28 = 1/56 tank/hour. After A and B fill for 7 hours, tank has 7/8 water. C empties 7/8 ÷ 1/56 = 49 hours. Option A (42) would require C's rate as 1/48, and Option B (45.5) is not consistent with the calculations.

Multiple choice
  1. 2

  2. 1

  3. 2.5

  4. 1.5

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Pipe A fills at 1/5 tank per hour. Pipe B fills at 1/6.25 = 4/25 tank per hour. Combined rate = 1/5 + 4/25 = 9/25 per hour. Let both pipes be open for t hours. Then A alone works for (3.4 - t) hours. Equation: (9/25)t + (1/5)(3.4 - t) = 1. Solving: (4/25)t = 0.32, so t = 2 hours. Option A is correct.

Multiple choice
  1. 600

  2. 1200

  3. 1800

  4. 900

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let the tank capacity be C gallons. The two inlet pipes fill at C/10 and C/12 gallons per hour. The drainage pipe empties 80 gallons/hour. Working together, their net rate is (C/10 + C/12 - 80) gallons/hour. Since they fill the tank in 20 hours: C/20 = C/10 + C/12 - 80. Solving: C/20 = 11C/60 - 80, so 3C = 11C - 4800, giving 8C = 4800, hence C = 600 gallons.

Multiple choice
  1. $3/5$
  2. $9/10$
  3. $3/10$
  4. $9/12$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Pipe A fills 1/16 of the tank per hour, and pipe B fills 1/20 per hour. Together they fill 1/16 + 1/20 = 9/80 per hour. In 8 hours, they fill 8 × (9/80) = 9/10 of the tank. Alternatively: in 8 hours, A fills 8/16 = 1/2 and B fills 8/20 = 2/5, so total = 5/10 + 4/10 = 9/10.

Multiple choice
  1. 16 hr.

  2. 12 hr.

  3. 10 hr.

  4. 8 hr.

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Combined rate: 1/8 tank per hour. Let P's rate = 1/x, Q's rate = 1/y. Given: P takes 4 hours longer than combined time, so x=12 hours. P's rate = 1/12. Q's rate = (1/8)-(1/12)=1/24. Therefore Q alone takes 24 hours, which is 16 hours longer than the combined 8 hours.