If the promisor absolutely repudiates the contract prior to the promised date of performance, it is

  1. frustration

  2. impossibility of performance

  3. final breach

  4. anticipatory breach

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

If the promisor prior to the due date of performance absolutely refuses or disables himself from the performance of obligations, it is anticipatory breach of contract.