Multiple choice technology testing

Which of the following is an activity in the fundamental test process?

  1. Test Planning and Design

  2. Test Analysis and Control

  3. Test Planning and Control

  4. Test execution and reoprting

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Test Planning and Control is indeed one of the fundamental activities in the test process according to ISTQB. The fundamental test process consists of planning and control, analysis and design, implementation and execution, evaluating exit criteria and reporting, and closure. Option A incorrectly says 'Planning and Design' which are separate phases. Option B incorrectly says 'Analysis and Control' - analysis is separate from planning/control. Option D has a typo ('reoprting') but also incorrectly names a phase.