Which of the following is a MAJOR task of test planning?

  1. Scheduling test analysis and design tasks.

  2. Initiating corrective actions.

  3. Monitoring progress and test coverage.

  4. Measuring and analyzing results.

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Test planning involves establishing the scope, objectives, risks, and overall schedule of testing activities. Scheduling test analysis and design tasks is a core planning activity. Distractors like monitoring progress, initiating corrective actions, or measuring results belong to test monitoring and control or test execution and evaluation phases, not initial test planning.