Multiple choice technology What is correct Software Process Cycle? Plan(P)------>Check(C)------>Act(A)----->Do(D) Plan(P)------>Do(D)------>Check(C)----->Act(A) Plan(P)------>Do(D)------>Act(A)----->Check(C) None Reveal answer Fill a bubble to check yourself B Correct answer Explanation The Plan-Do-Check-Act (PDCA) cycle follows the sequence: Plan (P) → Do (D) → Check (C) → Act (A). Option B correctly shows this order. This is the Deming Cycle/Shewhart Cycle used for continuous improvement in quality management.