Multiple choice technology packaged enterprise solutions

BOM workday Calendar which of the following weekly pattern

  1. 4/4/5

  2. 5/4/4

  3. Both Option 1 and 2

  4. 4/4/4

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Workday calendars support standard weekly patterns. 4/4/5 and 5/4/4 are common calendar split configurations used to divide a 52-week year into 13-week quarters. Both option 1 and option 2 are valid configurations, making option 3 correct.