Multiple choice technology packaged enterprise solutions

Which process message gets generated for the Line Hours Calculation Program?

  1. Z_PROD

  2. Z_PHCONS

  3. Z_MCHRS

  4. Z_CONS

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

The Line Hours Calculation Program generates process message Z_PHCONS, which is a custom message type specific to Kraft's SAP environment for phantom consumption processing. Z_PROD relates to production, Z_MCHRS to man hours, and Z_CONS is a general consumption message - none of these match the line hours program output.