The review and approved document (i.e. Test plan, System Requirement Specification’s) is called as

  1. Delivery Document

  2. Baseline Document

  3. Checklist

  4. None of the Above


Correct Option: B

AI Explanation

To answer this question, you need to understand the concept of document management in software development projects.

Option A) Delivery Document - This option is incorrect because a delivery document typically refers to a document that is used to deliver a product or service to a customer, not the review and approved document in question.

Option B) Baseline Document - This option is correct. A baseline document refers to a version of a document that has been reviewed, approved, and agreed upon as the official version. It serves as a reference point for future changes and is used as a basis for comparison during the project's lifecycle.

Option C) Checklist - This option is incorrect. A checklist is a tool used to ensure that all required tasks or items are completed or included. It is not the term used for the review and approved document in question.

Option D) None of the Above - This option is incorrect because option B, Baseline Document, is the correct answer.

The correct answer is B) Baseline Document. This option is correct because a baseline document represents the reviewed and approved version of a document in a software development project.