Multiple choice technology testing

Which test activities are supported by test data preparation tool

  1. test management & control,

  2. test specifications & design,

  3. test execution & logging,

  4. performance & monitoring

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Test data preparation tools support the test specification and design phase by helping create, manage, and prepare the data sets needed for test scenarios. They are not used for test management/control (A), execution/logging (C), or performance monitoring (D), which are separate testing activities.