Multiple choice technology testing

At start of the System Testing which Document is Prepared

  1. DTP(Detail Test Plan)

  2. MTP(Master Test Plan)

  3. STP(System Test Plan)

  4. Tracebility Matrices

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

At the start of System Testing, the System Test Plan (STP) is prepared. This document defines the scope, approach, resources, and schedule for system-level testing. DTP (Detail Test Plan) comes later for specific test cases, MTP (Master Test Plan) is for overall test strategy across all test levels, and Traceability Matrices are prepared during test planning.