Multiple choice technology testing

A release is equivalent to a RQM ------------------ and a project is equivalent to a RQM ------------

  1. Project and Test plan

  2. Test plan and Requirement

  3. Project and Requirement

  4. Requirement and test suite

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

In IBM Rational Quality Manager (RQM), a 'release' maps to a 'Project' and a 'project' maps to a 'Test plan'. This is the standard terminology mapping in RQM's hierarchical structure.