Multiple choice technology testing

Which activity is not a part of test estimation?

  1. Monitoring progress of tests runs

  2. Identifying test activities

  3. Planning for rework and retest cycle

  4. Estimating total effort to report faults

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Test estimation is a planning activity that occurs before test execution, involving forecasting resources, schedules, and scope. Monitoring test progress happens during execution and control, which is after estimation. Options B, C, and D are all valid estimation activities (identifying tasks, planning rework cycles, estimating defect reporting effort).