Pipes and Cisterns Questions

Multiple choice
  1. more than 20 filling pipes were installed

  2. Less than 19 filling pipes were installed

  3. Number of draining pipes was 7 more than the filling pipes

  4. More than one is true

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Interpreting the condition as n = 43, let f be the number of filling pipes and d the number of draining pipes. Solving f + d = 43 and f/15 - d/25 = 1/5 gives f = 18 and d = 25. Thus fewer than 19 filling pipes were installed, and the draining pipes were 7 more than the filling pipes, so more than one statement is true.

Multiple choice
  1. 9.8 hours

  2. 10.2 hours

  3. 10.5 hours

  4. 11.4 hours

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Net rate = 1/15 + 1/20 + 1/25 - 1/30 - 1/40. Common denominator = 600. Rate = (40 + 30 + 24 - 20 - 15) / 600 = 59 / 600. Time = 600 / 59 approx 10.17 hours.

Multiple choice
  1. 2332.8 cubic inches/min

  2. 194.4 cubic feet/hr

  3. 7.2 cubic yards/hr

  4. 17.28 cubic yards/hr

  5. 233.2 cubic yards/hr

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Volume = 2.4 * 2.0 * 1.5 = 7.2 cubic yards. 7.2 cubic yards = 7.2 * 46656 cubic inches = 335923.2 cubic inches. Time = 2 hrs 24 min = 144 minutes. Rate = 335923.2 / 144 = 2332.8 cubic inches/min.

Multiple choice
  1. 112 hours

  2. 224 hours

  3. 118 hours

  4. 236 hours

  5. None of the above

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Rate A = 1/28, Rate B = 1/32. Combined rate = 1/28 + 1/32 = (8+7)/224 = 15/224. Time = 224/15 hours = 14.933 hours = 896 minutes. With hole, time = 896 + 64 = 960 minutes = 16 hours. Combined rate - hole = 1/16. Hole rate = 15/224 - 1/16 = (15-14)/224 = 1/224. Hole takes 224 hours.

Multiple choice
  1. 6.9 hrs

  2. 9.6 hrs

  3. 8.4 hrs

  4. 9.4 hrs

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

The combined filling rate of pipes X and Y is 1/16 + 1/24 = 5/48 of the tank per hour. After the leak is closed, the tank takes 48/5 hours to fill completely, which means X and Y filled (5/48) * (48/5) = 1 (the entire tank) during this time. This implies that no water accumulated during the first 8/3 hours because the leak rate was exactly equal to the combined filling rate of 5/48. Thus, the leak alone can empty the full tank in 1 / (5/48) = 9.6 hours.

Multiple choice
  1. 19.6 minutes

  2. 19.2 minutes

  3. 18.8 minutes

  4. 18.4 minutes

  5. 17.2 minutes

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Pipe A fills 1/32 of the tank per minute, and pipes B and C together fill 1/12 per minute. Since C works twice as fast as A, its rate is 1/16, so B's rate is 1/48. Thus A and B together fill 5/96 of the tank per minute, taking 19.2 minutes.

Multiple choice
  1. 2.5 hrs

  2. 4 hrs

  3. 3 hrs

  4. 1/3 hrs

Reveal answer Fill a bubble to check yourself
C Correct answer
Multiple choice
  1. 1.5 hours

  2. 18 hours

  3. 20 hours

  4. 16 hours

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Rates: A = +1/4, B = -1/6, C = +1/8. Cycle (5 hours): Hr 1: +1/4. Hr 2: +1/4 - 1/6 = +1/12. Hr 3: -1/6. Hr 4: -1/6 + 1/8 = -1/24. Hr 5: +1/8. Net per cycle = 1/4 + 1/12 - 1/6 - 1/24 + 1/8 = (6+2-4-1+3)/24 = 6/24 = 1/4. After 3 cycles (15 hours), tank is 3/4 full. Hr 16: +1/4. Total = 1. Tank is full at 16 hours.

Multiple choice
  1. 18

  2. 36

  3. 27

  4. 24

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let the total work be 1 unit. A, B, C fill it in t minutes together, so rate A+B+C = 1/t. A and B together fill in t minutes, so rate A+B = 1/t. This implies C's rate is 0, which contradicts the problem. Re-reading: 'Each pipe fills an equal share of the tank'. This means each fills 1/3 of the tank. A works for the whole time T_total. B works for 10 mins. C works for (T_total - 12) mins. A's rate = (1/3) / T_total. B's rate = (1/3) / 10. C's rate = (1/3) / (T_total - 12). Since A+B fill in t minutes, (1/3T_total + 1/30) * t = 1. Solving these leads to T_total = 36. C's time = 36 - 12 = 24.

Multiple choice
  1. 60

  2. 32

  3. 24

  4. 40

Reveal answer Fill a bubble to check yourself
D Correct answer
Multiple choice
  1. 90

  2. 60

  3. 120

  4. 75

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A, B, and C be the rates of the pipes. Given 1/A + 1/C - 1/B = 1/2. Also, B = A - 1. Using the second condition, (1/C - 1/B) * 1 + 1/C * 1.25 = 1. Solving these equations leads to the rate of C, which results in a fill time of 90 minutes.