420000
-
240000
-
360000
-
260000
B
Correct answer
Explanation
0.50 hectare = 5000 sq.meter (since 1 hectare = 10,000 sq.meter). Cost = 5000 × 48 = 240,000. Always convert hectare to square meters first.
D
Correct answer
Explanation
Total perimeter = 5300 / 26.50 = 200m. Let breadth be x, length be x+20. 2(x + x + 20) = 200 => 4x + 40 = 200 => 4x = 160 => x = 40. Length = 40 + 20 = 60m. Since 60 is not listed, 'None of these' is correct.
-
10
-
11
-
12
-
None of the above
A
Correct answer
Explanation
Let length = x meters and cost per meter = Rs. y. Given xy = 35 and (x + 4)(y - 1) = 35. Expanding: xy - x + 4y - 4 = 35. Substituting xy = 35: 35 - x + 4y - 4 = 35, so 4y - x = 4. Since y = 35/x, we get 4(35/x) - x = 4, which gives x² + 4x - 140 = 0, so (x + 14)(x - 10) = 0. Therefore x = 10 meters.
-
Rs. 28080
-
Rs. 30800
-
Rs. 33264
-
Rs. 31104
-
None of these
C
Correct answer
Explanation
Area of 4 walls of the room = [2 x 14 x (10 + 12) ] sq. m = [28 x 22] sq. m = 616 sq. m
Therefore, cost of painting = Rs. ( 616 x 54 ) = Rs. 33264
-
Rs. 300
-
Rs. 1200
-
Rs. 3000
-
Rs. 30000
-
None of these
C
Correct answer
Explanation
Total surface area of the cube = 6 x 5 m x 5 m = 150 sq. m
Therefore, cost of painting the cube = Rs. (20 x 150) = Rs. 3000
-
Rs. 800
-
Rs. 80
-
Rs. 1600
-
Rs. 960
-
None of these
C
Correct answer
Explanation
Area to be painted = 2 (lb) = (2 x 10 x 8) sq. cm = 160 sq. cm
Cost of painting = Rs. (10 x 160) = Rs. 1600
-
Rs. 100
-
Rs. 200
-
Rs. 160
-
Rs. 240
-
None of these
B
Correct answer
Explanation
Total area to be painted = 2 (lh) = (2 x 10 x 2) sq. cm = 40 sq cm
Cost of painting = Rs. (5 x 40) = Rs. 200
-
Rs. 2320
-
Rs. 1160
-
Rs. 1392
-
Rs. 580
-
None of these
C
Correct answer
Explanation
Total surface area of the cuboid = 2 (lb + bh + hl) = 2 (10 x 8 + 8 x 2 + 2 x 10) sq. cm = 2 (80 + 16 + 20) sq. cm = 2 (116) = 232 sq. cm
Cost of painting = Rs. (6 x 232) = Rs. 1392
-
Rs. 1392
-
Rs. 1160
-
Rs. 2320
-
Rs. 580
-
None of these
B
Correct answer
Explanation
Total surface area of the cuboid = 2 (lb + bh + hl) = 2 (10 x 8 + 8 x 2 + 2 x 10) sq. cm = 2 (80 + 16 + 20) sq. cm = 2 (116) = 232 sq. cm
Cost of painting = Rs. (5 x 232) = Rs. 1160
-
Rs. 6032
-
Rs. 6496
-
Rs. 6022
-
Rs. 3016
-
None of these
A
Correct answer
Explanation
Total surface area of 1 cuboid = 2 (lb + bh + hl) = 2 (10 x 8 + 8 x 2 + 2 x 10) sq. cm = 2 (80 + 16 + 20) sq. cm = 2 (116) = 232 sq. cm
Total surface area of 2 such cuboids which is to be painted red = 2 x 232 sq cm = 464 sq. cm and the cost of painting will be Rs. (464 x 5) = Rs. 2320
Also, cost of painting 1 cuboid with green colour = Rs. (232 x 6) = Rs. 1392.
Again, cost of painting 1 cuboid with yellow colour = Rs. (232 x 10) = Rs. 2320
Therefore, total cost of painting = Rs. (2320 + 1392 + 2320) = Rs. 6032
-
Rs. 50,000
-
Rs. 5,50,000
-
Rs.25,000
-
nil
C
Correct answer
Explanation
Repair costs (Rs. 15,000) and whitewash expenses (Rs. 10,000) are revenue expenditures that benefit the current period and must be expensed immediately. The building extension (Rs. 5,00,000) and electrical wiring improvement (Rs. 25,000) are capital expenditures that enhance the asset's value and must be capitalized. Total expense = Rs. 15,000 + Rs. 10,000 = Rs. 25,000. Options A and B incorrectly include capital expenditures.
-
Rs. 2375
-
Rs. 2325
-
Rs. 2350
-
Rs. 2500
-
None of these
A
Correct answer
Explanation
Area of hall = 25*20 = 500 sq. metres
Length of hall with veranda = 25 + 5 = 30 m
Breadth of hall with veranda = 20 + 5 = 25 m
Area of hall with veranda = 30*25 = 750 sq. metres
Then, area of veranda = 750 - 500 = 250 sq. metres
Cost of flooring = 250*9.50 = Rs. 2375
D
Correct answer
Explanation
This is the correct answer. The total cost of fencing is Rs. 7200. The rate of fencing is Rs. 12/m.
Perimeter x rate of fencing = total cost
Perimeter = total cost/rate = 7200/12 = 600 m
Length = 175
Breadth = ?
Perimeter = 600
P = 2(L + B)
600 = 2(175 + b) = 350 + 2b
600 - 350 = 2b
250 = 2b
b = 250/2 = 125 m
-
20 cm
-
12.5 cm
-
900 cm
-
15.2 cm
-
-
B
Correct answer
Explanation
This is the correct answer.
Total cost of flooring = Rs. 1700
Rate of flooring = Rs. 8.50 per m2
Area of the floor = Total cost/Rate per square metre = 1700/8.50 = 200 m2
Breadth of the room = Area/Length = 200/16 = 12.5 cm
-
Rs. 12.5
-
Rs. 15.2
-
Rs. 125
-
Rs. 152
-
-
A
Correct answer
Explanation
This is the correct answer.
Area of the square plot = 2.5 x 2.5 = 6.25 m2
Cost of levelling = Area x rate per metre = 6.25 x 2 = Rs. 12.5