X,Y,and Z take 20, 30 and 60 days respectively to complete a job independently. They set out to complete a job together . However Y leaves after 4 days and Z leaves after another 6 days . How many more days will it take for X alone to complete the job now?

general knowledge math & puzzles
  1. 4

  2. 3

  3. 5

  4. 6


Show answer
Correct Option: A