Multiple choice

A maintenance department has supply of commodities for 72 engineers for a period of 54 days. The supply of commodities gets reduced by 10% when 18 more engineers come to work. Find out the number of days for which the engineers will have to work.

  1. 43.2 days

  2. 48 days

  3. 108 days

  4. 43.02

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

72 * 54/90 * 9 = 48 because 10% of the supply is reduced.