Multiple choice

A team of 24 men is supposed to do a job in 36 days. After 28 days, some more men are employed and work was finished 4 days earlier. Then how many more men were employed ?

  1. 28

  2. 21

  3. 24

  4. 19

  5. N/A

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

24 men can do the job in 36 days After employing some more men work of (36 -28) = 8 days was finished in 8- 4 days Total no. of men = 8x 24 /4 = 48 Therefore required no. of more men = 48- 24 men.