Multiple choice

In 2008, ____ along with two Chinese power equipment majors — Dong Fang Electric (DEC) and Sepco Electric Power Construction were competing for the Rs 2,400 crore EPC (engineering, procurement and construction) contract for CESC's 600 mw Haldia (Phase I) thermal venture.

  1. BHEL

  2. NTPC

  3. L & T

  4. IECC

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

BHEL (Bharat Heavy Electricals Limited) was the primary Indian competitor against the Chinese firms for the Haldia thermal power project contract in 2008.