The sum of direct materials and direct labour costs is called

  1. Prime Cost

  2. Factory Cost

  3. Overhead Cost

  4. Value of Stock

  5. Full Cost

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Prime Cost is defined as the sum of direct materials cost and direct labour cost. This is a standard cost accounting concept. Factory Cost includes additional overheads, Overhead Cost refers to indirect costs, and Value of Stock refers to inventory valuation.