Multiple choice test management

Test managers should not:

  1. Sign the system off for release

  2. Report on deviations from the project plan

  3. Re-allocate resource to meet original plans

  4. Raise incidents on faults that they have found

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Test managers should report deviations, raise incidents, and sign off for release based on quality criteria. However, blindly reallocating resources to meet original plans when circumstances have changed is poor management practice. Plans should adapt to reality, not the other way around. Forcing resource reallocation to meet outdated dates can compromise quality.