Multiple choice Penalties under contract for delay in completion of a contract on schedule are known as liquidated damages container liability construction liability fidelity guarantee Reveal answer Fill a bubble to check yourself A Correct answer Explanation Liquidated damage is an estimated amount equal to the extent of injury that may occur, if the contract is breached. These damages are determined when a contract is drawn up and serve as protection for both parties that have entered the contract.