Which of the following is a hierarchic decomposition of a project or major activity into successive levels?

  1. PERT chart

  2. Manageable task

  3. Work breakdown structure

  4. Interoperability

  5. Controlling

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

 It is a hierarchic decomposition of a project or major activity into successive levels.

Keep practicing — related questions

  • In this structure work is organized around specific projects
  • Which of the following organisations exists of a matrix with dominant project structure and underlying the ...
  • Which kind of planning consists of successive representations of different levels of a plan?
  • Which of the following is basically a method to analyze the tasks involved in completing a given project, e...
  • Which helps in scheduling the activities of a project, but it does not help in identifying them?
  • Which organizational structure is based on the concepts of division of labours, specialization and unity of...
  • In which of the following RAID levels is the error detection done by block level parity and is stored in se...
  • In which of the following models for object activation defined by basic object adapter do multiple active o...
Play the full quiz 🎤 Practise this topic out loud

Practice this topic

  • Software Development and Management (3064 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy