Multiple choice

Which of the following is basically a method to analyze the tasks involved in completing a given project, especially the time needed to complete each task and identifying the minimum time needed to complete the total project?

  1. Manageable Task

  2. Work Breakdown Structure

  3. Gantt Chart

  4. Automated Software Synthesis

  5. PERT Chart

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

It is a basically method to analyze the task involved in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project.