Multiple choice

Which CMM level certifies that the process is quantitatively managed in accordance with agreed upon metrics?

  1. Level 7

  2. Level 4

  3. Level 1

  4. Level 2

  5. Level 3

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

It is characteristic of processes at this level that, using process metrics, management can effectively control the AS-IS process (e.g., for software development ). In particular, management can identify ways to adjust and adapt the process to particular projects without measurable losses of quality or deviations from specifications. Process capability is established from this level.