Multiple choice

Which of the following is the metric in a form suitable for assessing project behavior or process improvements?

  1. Size oriented metrics

  2. Indicators

  3. Planned value

  4. Actual cost

  5. Objective statement

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Indicators are metrices in a form suitable for assessing project behavior or process improvements.