Multiple choice

Software project planning is involved in _____ process level of Capability Maturity Model.

  1. initial

  2. repeatable

  3. defined

  4. managed

  5. none of the above

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

This process includes the software project planning as it is the basic management process, in which the cost, schedule and functionality of the software is analysed to repeat earlier processes to other applications also.