Multiple choice

In which of the following process maturity levels of CMM, a basic project management process is established to track cost, schedule and functionality?

  1. Initial

  2. Managed

  3. RAID level 1

  4. RAID level 2

  5. Repeatable

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

In this process maturity level of CMM, basic project management processes are established to track cost, schedule and functionality.