Integration, It will come under
-
CMM Level 1
-
CMM Level 3
-
CMM Level 2
-
None
B
Correct answer
Explanation
CMM Level 3 (option B) is the Defined level where organizations have standard processes for both development and maintenance, including integration. Level 1 is Initial (ad-hoc). Level 2 is Repeatable (basic project management). Integration requires standard processes, placing it at Level 3.